When: Sunday, September 29, 2024, 06:00 AM to 06:00 PM
Where: Lima Estate including Rosewood, Palmdale,Sunnyvale and Campo Verde Subdivisions.
Why: The scheduled Power Interruption is initiated by NGCP for the following activities :
a. General Maintenance & Testing of Batangas Limaland 69KV Line 1 associated HVES.
b. Preventive Maintenance of Main Protection.
c. Preventive Maintenance of SAS / Integrated MSBC & IED Meter.
In relation to the above scenario, Lima EnerZone will take the oppurtunity to facilitate
the activities below:
a. Pole relocation located at Block 9 as per customer’s request.
b. 69 KV Pole Relocation located at Bugtong na Pulo, Lipa City
as mandated by DPWH.
c. Substation and OHDL Maintenances.