Service Interruption: November 15, 2026

Oct 30
1 min read

Updated: Nov 5

WHEN

November 15, 2026, Sunday - 6:00 AM to 6:00 PM

WHY

The scheduled power interruption is initiated by NGCP for the Annual Preventive Maintenance.

  1. Testing of Batangas-Limaland 69kV Line 1 associated HVE

  2. General Maintenance of Batangas-Limaland 69kV Line 1 associated HVE


In relation to the above scenario, LEZC will take the opportunity to facilitate the below activities: 

  1. Preventive Maintenance of Substation 2 and Distribution Line Maintenances

WHERE

Lima Estate’s Industrial, Commercial & Residential Customers specifically Campo Verde, Rosewood, Palmdale 1&2, Sunnyvale 1&2