Service Interruption: April 6, 2025

  • Mia Concepcion
  • Mar 18
  • 1 min read

๐—ช๐—›๐—˜๐—ก: Sunday, April 6, 2025, from 06:00 AM to 06:00 PM.


๐—ช๐—›๐—˜๐—ฅ๐—˜: Lima Estate including Rosewood, Palmdale, Sunnyvale, and Campo Verde Subdivisions.


๐—ช๐—›๐—ฌ: The scheduled power interruption is initiated by NGCP for the following activities:


a. NGCPโ€™s General Maintenance and Testing of HVEs.


In relation to the above scenario, LEZC will take the opportunity to facilitate the below activities:


a. Commissioning of the repaired 69kV Power Cable

b. Commissioning of LEZ TR1

c. Load transfer of Feeders to its original connection

d. Other substation and distribution maintenances