Service Interruption: April 2, 2026

  • Mar 13
  • 1 min read

WHEN

 Thursday, April 2, 2026 - 06:00 AM to 06:00 PM

WHY

To facilitate the request for Block 21A, Lot 1, Campo Verde Subdivision. Upon inspection, it was determined that the primary line encroached the customers aerial property. To prevent potential public safety and operational hazard, reconfiguration of the power line is therefore necessary.

WHERE

To facilitate the following activities:

1. High Voltage Equipment Maintenance

2. Commissioning and Energization of 69kV Underground Power Cable

3. Hotspot Corrections

4. Correction of PEMC Findings