Apply for Electrical Connection
New Connection Requirements
TECHNICAL REQUIREMENTS (A3 Size)
-
Approved Electrical Plan indicating transformer size (signed & sealed by PEE)
-
Scaled Site Development Plan
-
Detailed design of pedestal/tapping point
-
Installation of Service Entrance/Metering Set–up
-
Lot boundaries with PS marks
METER INSTALLATION REQUIREMENTS
-
Certificate of Final Electrical Inspection/Completion (PEZA/OBO/LGU)
-
Contract to Sell/Deed of Absolute Sale (photocopy)
-
Lease/Sub–Lease Contract/Deed of Assignment (for non-owners)
-
Transformer Test Report
-
Transformer TDS
-
Transformer Banking Configuration
-
Duly Signed Electric Service Agreement & Customer Consent Form
REQUIREMENTS FOR COMPANY OR CORPORATION
-
PEZA Certificate of Registration/PEZA Permit to Locate/Business Permit (2 Copies)
-
BIR 2303 (2 Copies)
-
SEC Registration
-
Articles of Incorporation
-
Board Resolution/Secretary’s Certificate (appointing representative to sign documents)
REQUIREMENTS FOR VAT ZERO RATING (Export Enterprise only)
-
PEZA Certificate of Registration (PEZA CTC)
-
Valid PEZA VAT Zero Rating Certificate (PEZA CTC)
-
BIR 2303
-
Sworn Affidavit
REQUIREMENTS FOR SOLE PROPRIETOR
-
Certificate of Registration from PEZA (2 Copies)
-
Certificate of Registration from DTI (2 Copies)
-
BIR 2303 (2 Copies)
OTHER REQUIREMENTS
-
Written request letter
-
Duly Filled out Application Form
-
Photocopy of two (2) valid IDs of Authorized Signatory
-
Special Power of Attorney (appointing representative to sign documents)
-
Endorsement/Certification from Developer (Lima Land, Inc
-
Undertaking (Applicable for Tenants)
-
Bill Deposit
-
For Contractors: Endorsement Letter from Servicing Entity
-
Other specified by the assigned Operations Engineer